Demonstration Plant: Concentrator Circuit Update - Phase One Complete

The concentrator circuit has now completed testwork on 500 t of ore with a further 2,500 – 3,000 t of ore to be finalised shortly.

The circuit has upgraded cobalt in ore to ~4,300 ppm in concentrate (with 75% mass rejection) – representing an ~5x upgrade. The Kiln circuit has now been commissioned, with leach and MHP production circuits to follow shortly.

Downloads

Full announcement Download PDF